Wood Harbinger provided a total electrical service upgrade for Building W-2 at Terminal 115 to accommodate the storage and maintenance of Northland Service’s refrigerated containers.

The project included new 15kV service drop coordination with Seattle City Light, and numerous coordination issues with existing utilities and the Burlington Northern Railroad.

Our services included:
  • Detailed field investigation;
  • Code-required service load and fault-current calculations; and
  • New electrical distribution system for Building W-2.